26 Kasım 2008 Çarşamba

Volume 3

Date: 21.11.2008

Time: 17:00 - 17:35
Prepared By: Erol Mesut Gün
Participants: Erol Mesut Gün, Çağlar Kara

This was the third interview with M. T., we talked about general concerns of M. T. about the documents that we have prepared and general assesment of what we have achieved so far. Main topics are:

  1. 1. Preperation of “on paper prototype drawings”, within 1-2 weeks and before the composition of use-cases, is required.
  2. 2. After the preperation of “on paper prototype drawings”, interview with M. A. (customer) will be held.
  3. 3. M. T. (boss) emphasized the importance of “creating slack times” on the project schedule. And we decided to revise the schedule (to-do list) in the light of this perspective.
  4. 4. M. T. (boss) mentioned about some required modifications on the “Summary of Project Deliverables”.
  5. 5. Çağlar Kara (project manager of Lothusa-IT team) noticed that we forgot to add the “Project Requirements” into the “Scope Statement”.
  6. 6. We (Erol Mesut Gün and Çağlar Kara) touched on the future of Lothusa-IT team and we conveyed our concerns about Gülin Sonuç.
  7. 7. M. T. appreciated our performance.